Manufacturing Lead Time Reduction of Gear Box Side Frame Using Lean Principles

  • Author:
  • G. Hari1, N. Sandeep2, Kishan Doss3
  • Total Page Count: 8
  • Page Number: 25 to 32

1M. Sc. [Engg.] Student, Department of Mechanical and Manufacturing Engineering, M.S. Ramaiah School of Advanced Studies, Bangalore, 560 058

2Asst. Professor, Department of Mechanical and Manufacturing Engineering, M.S. Ramaiah School of Advanced Studies, Bangalore, 560 058

3Director, Operations Searock Precision Products Pvt. Ltd, Bangalore

Online published on 18 February, 2020.

Abstract

In today's high pressure market slashing lead time is the fastest and most powerful approach to profitability improvement, especially for companies who have already realized most of their core manufacturing efficiency improvement opportunities. Lead time reductions will directly impact almost every contributor to costs within the company's operations. With its strategic importance Lead time reduction has become an important element of campaign to increase the competitiveness of manufacturing industry

The objective of the study is to reduce the lead time of the side cover. The initial phase of study included the construction of a macro process map. Macro time study revealed process that has higher cycle time than Takt time. Micro process mapping and micro time study was conducted to look up on wastages in processes. Root cause analysis was carried out to find out the causes of the excess waste. Solutions to the problem were found by implementing a dedicated fixture, tool trolley, SOP, and 5S

The result showed a significant reduction in lead time of the component with an average reduction of 15% of the lead time. The use of the fixture along with tool trolley significantly reduced the process time of the concerned process by about 38%. The implementation of fixture brought in this significant improvement in lead time without the addition of an extra machine or a negative impact on quality. Future recommendation was also provided that would further reduce the total lead time of the process.

Keywords

Lead Time, Gear Box, Lean Principle